Search icon

BONICHE STRUCTURAL CORP - Florida Company Profile

Company Details

Entity Name: BONICHE STRUCTURAL CORP
Jurisdiction: FLORIDA
Filing Type: Domestic Profit

BONICHE STRUCTURAL CORP is structured as a Domestic Profit Corporation, which, in Florida signifies a Profit Corporation (also known as a C-Corporation). This business structure is recognized as a separate legal entity from its owners. This offers shareholders the benefit of limited liability protection, safeguarding their personal assets from the corporation's debts and obligations, and facilitates raising capital through the issuance of stock. In Florida, Domestic Profit Corporations are governed by Title XXXVI, Chapter 607, Florida Statutes – Florida Business Corporation Act.

Status: Active

The business entity is active. This status indicates that the business is currently operating and compliant with state regulations, suggesting a lower risk profile for lenders and potentially better creditworthiness.

Date Filed: 09 Jan 2019 (6 years ago)
Last Event: REINSTATEMENT
Event Date Filed: 26 Oct 2020 (4 years ago)
Document Number: P19000003723
FEI/EIN Number 83-3144711

Federal Employer Identification (FEI) Number assigned by the IRS.

Address: 12315 SW 254TH TERR, HOMESTEAD, FL, 33032
Mail Address: 12315 SW 254TH TERR, HOMESTEAD, FL, 33032
ZIP code: 33032
County: Miami-Dade
Place of Formation: FLORIDA

Key Officers & Management

Name Role Address
BONICHE PAUL A Agent 12315 SW 254TH TERR, HOMESTEAD, FL, 33032
BONICHE PAUL A President 12315 SW 254TH TERR, HOMESTEAD, FL, 33032

Events

Event Type Filed Date Value Description
REINSTATEMENT 2020-10-26 - -
REGISTERED AGENT NAME CHANGED 2020-10-26 BONICHE, PAUL A -
ADMIN DISSOLUTION FOR ANNUAL REPORT 2020-09-25 - -

Documents

Name Date
ANNUAL REPORT 2024-03-08
ANNUAL REPORT 2023-02-20
ANNUAL REPORT 2022-03-18
ANNUAL REPORT 2021-01-28
REINSTATEMENT 2020-10-26
Domestic Profit 2019-01-09

OSHA's Inspections within Industry

Inspection Nr Report ID Date Opened Site Address
344050067 0418800 2019-05-22 6320 SW 8TH STREET SOLESTE ALAMEDA 1, MIAMI, FL, 33101
Inspection Type Unprog Rel
Scope Partial
Safety/Health Safety
Close Conference 2019-05-31
Emphasis L: OHPWRLNE
Case Closed 2023-04-13

Related Activity

Type Inspection
Activity Nr 1409648
Safety Yes
Type Inspection
Activity Nr 1409632
Safety Yes
Type Inspection
Activity Nr 1409643
Safety Yes

Violation Items

Citation ID 01001A
Citaton Type Serious
Standard Cited 19261408 A02
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 9282.0
Initial Penalty 9282.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1408(a)(2): The employer did not determine if any part of the equipment, load line or load (including rigging and lifting accessories), if operated up to the equipment's maximum working radius in the work zone, could get closer than 20 feet to a power line: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, employees were exposed to an electrocution hazard while a tower crane was operating with its load line and load located at a distance closer than 20 feet from energized electrical lines. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01001B
Citaton Type Serious
Standard Cited 19261408 A02 I
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1408(a)(2)(i): Option (1)-Deenergize and ground. The employer failed to confirm from the utility owner/operator that the power line has been deenergized and visibly grounded at the worksite: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, the employer failed to ensure de-energization and grounding of electrical utilities, while operating a tower crane with a load line and load near energized electrical power lines, thus exposing employees to an electrocution hazard. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01001C
Citaton Type Serious
Standard Cited 19261408 A02 II
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1408(a)(2)(ii): The employer failed to ensure that no part of the equipment, load line, or load (including rigging and lifting accessories), gets closer than 20 feet to the power line by implementing the measures specified in paragraph (b) of this section. Reference Option (2)-20 foot clearance: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, the employer failed to ensure a load line and load for a tower crane were kept further away than 20 feet from power lines, thus exposing employees to an electrocution hazard. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01001D
Citaton Type Serious
Standard Cited 19261408 A02 III
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1408(a)(2)(iii): Option (3)-Table A clearance. The employer failed to determine the line's voltage and the minimum approach distance permitted under Table A (see 29 CFR 1926.1408): On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, the employer failed to ensure the load line and load of a tower crane were maintained a distance away from energized power lines with the use of recommendations made by the utility owner or registered professional engineer, thus exposing employees to an electrocution hazard. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01001E
Citaton Type Serious
Standard Cited 19261408 D01
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1408(d)(1): Part(s) of equipment, load line, or load (including rigging and lifting accessories) were allowed below an energized power line when the acceptions to paragraph (d)(2) did not apply: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, employees were exposed to an electrocution hazard while operating a tower crane with its load line, load, and parts below energized power lines. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01002
Citaton Type Serious
Standard Cited 19261408 G01 I
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 9282.0
Initial Penalty 9282.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1408(g)(1)(i): The employer failed to train the crane operator and each crane crew member, in the procedures to be followed in the event of electrical contact with a power line. Such training must include the requirements of: 1926.1408(g)(1)(i)(A) through (g)(1)(i)(F): On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, employees were exposed to an electrocution hazard while operating a tower crane near energized electrical lines and not receiving training in the procedures to follow in the event the load, load, and parts made physical contact with the power lines. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01003A
Citaton Type Serious
Standard Cited 19261428 A
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 9282.0
Initial Penalty 9282.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1428(a): The employer of the signal person did not ensure that each signal person met the Qualifications Requirements (paragraph (c) of this section) prior to giving any signals: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, the employer failed to train a signal person in giving signals to a tower crane operator prior to a tower crane operating near energized electrical lines, thus exposing employees to an electrocution hazard. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01003B
Citaton Type Serious
Standard Cited 19261428 C03
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1428(c)(3): The employer of the signal person did not ensure that each signal person had a basic understanding of equipment operation and limitations, including the crane dynamics involved in swinging and stopping loads and boom deflection from hoisting loads: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, the employer failed to train a signal person to understand the operation, limitations, rotational and pendular movement of loads for a tower crane that was operating near energized electrical lines, thus exposing employees to an electrocution hazard. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01003C
Citaton Type Serious
Standard Cited 19261428 C05
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1428(c)(5): Each signal person did not demonstrate that he/she meet the requirements in paragraphs (c)(1) through (4) of this section through an oral or written test, and through a practical test: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, the employer failed to evaluate a signal person prior to providing signals to a tower crane operator while the loads and load line of the equipment were operating near energized electrical lines, thus exposing employees to an electrocution hazard. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.
Citation ID 01003D
Citaton Type Serious
Standard Cited 19261430 G01
Issuance Date 2019-10-18
Abatement Due Date 2019-11-14
Current Penalty 0.0
Initial Penalty 0.0
Final Order 2019-11-18
Nr Instances 2
Nr Exposed 1
Related Event Code (REC) Referral
Gravity 10
FTA Current Penalty 0.0
Citation text line 29 CFR 1926.1430(g)(1): The employer did not evaluate each employee required to be trained under this subpart to confirm understanding of the training: On or about April 22, 2019, at 6320 SW 8th Street, Miami, Florida, 33101, the employer failed to evaluate an operator of a tower crane while the loads and load line of the equipment were operating near energized electrical lines, thus exposing employees to an electrocution hazard. NOTE: CERTIFICATION AND DOCUMENTATION OF ABATEMENT IS REQUIRED FOR THIS VIOLATION.