Inspection Type |
Planned
|
Scope |
Complete
|
Safety/Health |
Safety
|
Close Conference |
2012-07-24
|
Emphasis |
N: TRENCH
|
Case Closed |
2013-11-27
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19260651 B01 |
Issuance Date |
2012-08-10 |
Current Penalty |
1800.0 |
Initial Penalty |
2400.0 |
Final Order |
2012-08-24 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.651(b)(1): The estimated location of underground utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work, were not determined prior to opening an excavation: a. On or about July 24, 2012, on the north side of the building, the underground sewer lines were not determined prior to digging the trench, the backhoe operator punctured 42-inch sewer line allowing water to enter the trench, exposing employees to a trench collapse hazard. |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19260651 B02 |
Issuance Date |
2012-08-10 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2012-08-24 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.651(b)(2): Utility companies or owners shall be contacted within established or customary local response times, advised of the proposed work, and asked to establish the location of the utility underground installations prior to the start of actual excavation. When utility companies or owners cannot respond to a request to locate underground utility installations within 24 hours (unless a longer period is required by state or local law), or cannot establish the exact location of these installations,the employer may proceed, provided the employer does so with caution, and provided detection equipment or other acceptable means to locate utility installations are used. a. On or about July 21, 2012, on the north side of the building, the underground sewer lines were not determined or verified prior to digging trench, the backhoe operator punctured 42-inch sewer line allowing water to enter the trench, exposing employees to a trench collapse hazard. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260651 C02 |
Issuance Date |
2012-08-10 |
Current Penalty |
1200.0 |
Initial Penalty |
1200.0 |
Final Order |
2012-08-24 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
1 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.651(c)(2): A stairway, ladder, ramp or other safe means of egress was not located in trench excavations that were 4 feet (1.22m) or more in depth so as to require no more than 25 feet (7.62m) of lateral travel for employees: a. On or about July 24, 2012, on the north side of the building in the 5-foot trench, a ladder or other safe means of access and egress was not provided, exposing employees to a fall hazard. |
|
Citation ID |
01003 |
Citaton Type |
Other |
Standard Cited |
19260651 H01 |
Issuance Date |
2012-08-10 |
Current Penalty |
0.0 |
Initial Penalty |
2400.0 |
Final Order |
2012-08-24 |
Nr Instances |
1 |
Nr Exposed |
2 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.651(h)(1): Employees were working in excavations in which there was accumulated water, or excavations in which water was accumulating, and adequate precautions had not been taken to protect employees against the hazards posed by water accumulation: a. On or about July 24, 2012, on the north side of the building, in a 5-foot deep trench, adequate precautions for water accumulation were not taken, exposing employees to a trench collapse hazard. |
|
Citation ID |
01004 |
Citaton Type |
Serious |
Standard Cited |
19260651 J02 |
Issuance Date |
2012-08-10 |
Current Penalty |
1800.0 |
Initial Penalty |
2400.0 |
Final Order |
2012-08-24 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.651(j)(2): Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary: a. On or about July 24, 2012, on the north side of the building, in a 5-foot trench, the spoil piles were not placed at least 2-foot back from the edge, exposing employees to the hazards of a trench collapse. |
|
Citation ID |
01005A |
Citaton Type |
Serious |
Standard Cited |
19260651 A |
Issuance Date |
2012-08-10 |
Current Penalty |
1800.0 |
Initial Penalty |
2400.0 |
Final Order |
2012-08-24 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.651(a): All surface encumbrances that were located so as to create a hazard to employees were not removed or supported, as necessary, to safeguard employees: a. On or about July 24, 2012, on the north side of the building, the 5-foot trench did not have all necessary all surface encumbrances removed or supported to safe guard employees, exposing them to a trench collapse hazard. |
|
Citation ID |
01005B |
Citaton Type |
Serious |
Standard Cited |
19260652 A01 |
Issuance Date |
2012-08-10 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2012-08-24 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.652(a)(1): Each employee in an excavation was not protected from cave-ins by an adequate protective system designed in accordance with 29 CFR 1926.652(c): a. On or about July 24, 2012, on the north side of the building, the 5-foot trench did not have adequate protective systems, exposing employees to a trench collaspe hazard. |
|
|