Inspection Type |
Planned
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2023-12-08
|
Emphasis |
N: FALL, P: FALL
|
Case Closed |
2024-05-02
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260451 C02 I |
Issuance Date |
2024-04-05 |
Current Penalty |
3457.0 |
Initial Penalty |
3457.0 |
Final Order |
2024-05-02 |
Nr Instances |
3 |
Nr Exposed |
3 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(c)(2)(i): Footings were not level, sound, rigid and capable of supporting the loaded scaffold without settling or displacement: a.) On or about December 8, 2023, westside of construction site: employees were conducting plastering and stucco work on scaffolding and two of the baseplates were not centered on the mudsills and were hanging over the edge. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19260451 G01 |
Issuance Date |
2024-04-05 |
Current Penalty |
3457.0 |
Initial Penalty |
3457.0 |
Final Order |
2024-05-02 |
Nr Instances |
6 |
Nr Exposed |
3 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(g)(1): Employees on scaffolds more than 10 feet (3.1 m) above a lower level were not protected from falling to that lower level by fall protection established in paragraphs (g)(1)(i)-(vii) of this section: a.) On or about December 8, 2023, at the jobsite: employees were conducting plastering and stucco work on scaffolding that did not have guardrails. Three workers were working at various heights on different sections of the scaffolding measuring from approximately 13 feet and 21 feet. |
|
Citation ID |
01003 |
Citaton Type |
Serious |
Standard Cited |
19260451 H01 |
Issuance Date |
2024-04-05 |
Current Penalty |
2765.0 |
Initial Penalty |
2765.0 |
Final Order |
2024-05-02 |
Nr Instances |
3 |
Nr Exposed |
3 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(h)(1): Each employee on a scaffold was not provided with additional protection from falling hand tools, debris, and other small objects through the installation of toeboards, screens, guardrail systems, or through the erection of debris nets, catch platforms, or canopy structures that contain or deflect the falling objects. For falling objects too large, heavy or massive to be contained or deflected, the employer did not place and secure such potential falling objects away from the edge of the surface from which they could fall. a.) On or about December 8, 2023, at the west side of the construction site: employees were conducting plastering and stucco work working from a tubular welded frame scaffold without toe boards being installed where other employees were exposed to falling debris from the plastering and stucco work that was being conducted at the time. |
|
|
Inspection Type |
Planned
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2017-05-22
|
Emphasis |
P: FALL, L: FALL
|
Case Closed |
2018-03-21
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260300 B03 |
Issuance Date |
2017-08-15 |
Current Penalty |
1912.2 |
Initial Penalty |
3187.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.300(b)(3): One or more methods of machine guarding were not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks: On or about May 22, 2017, at the above addressed jobsite, an employee was exposed to the amputation hazard while putting his hand to a point of operation in order to turn on a concrete mixer that the yoyo broke and the guard was removed. |
|
Citation ID |
01002A |
Citaton Type |
Serious |
Standard Cited |
19260451 B01 II |
Issuance Date |
2017-08-15 |
Current Penalty |
1912.2 |
Initial Penalty |
3187.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(b)(1)(ii): The platform was not planked or decked as fully as possible and the remaining open space between the platform and the uprights exceeded 9.5 inches (24.1 cm): On or about May 22, 2017, at the above addressed jobsite, employees were exposed to an 8 feet fall hazard while working from a welded tubular scaffold not fully planked. |
|
Citation ID |
01002B |
Citaton Type |
Serious |
Standard Cited |
19260451 F07 |
Issuance Date |
2017-08-15 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration. Such activities were not performed only by experienced and trained employees selected for such work by the competent person: On or about May 22, 2017 at the above addressed jobsite, employees were exposed to an 8-foot fall hazard while performing plastering work from a scaffold not erected by a competent person. |
|
Citation ID |
01003A |
Citaton Type |
Serious |
Standard Cited |
19260451 C02 |
Issuance Date |
2017-08-15 |
Current Penalty |
1912.2 |
Initial Penalty |
3187.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, or uprights did not bear on base plates, mud sills or other adequate firm foundation: On or about May 22, 2017, at the above addressed jobsite, employees were working from an 8-foot welded tubular scaffold that was missing base plates and supported on concrete blocks. |
|
Citation ID |
01003B |
Citaton Type |
Serious |
Standard Cited |
19260454 B02 |
Issuance Date |
2017-08-15 |
Abatement Due Date |
2017-08-25 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.454(b)(2): The employer did not have each employee who was involved in erecting, disassembling, moving, operating, repairing, maintaining, or inspecting a scaffold trained by a competent person to recognize any hazards associated with the correct procedures for erecting, disassembling, moving, operating, repairing, inspecting, and maintaining the type of scaffold in question: On or about May 22, 2017, at the above addressed jobsite, employees were not train on to recognize any hazards associated with a welded tubular scaffold. |
|
Citation ID |
01004 |
Citaton Type |
Serious |
Standard Cited |
19260451 E01 |
Issuance Date |
2017-08-15 |
Current Penalty |
1912.2 |
Initial Penalty |
3187.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access: On or about May 22, 2017, at the above addressed jobsite, employees were exposed to an 8-foot fall hazard while accessing work areas using the side of a welded tubular scaffold as a ladder. |
|
Citation ID |
02001 |
Citaton Type |
Other |
Standard Cited |
19100134 K06 |
Issuance Date |
2017-08-15 |
Abatement Due Date |
2017-10-02 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.134(k)(6): The employer did not provide the basic advisory information on respirators, as presented in Appendix D of 29 CFR 1910.134, in written or oral format to employees who wear respirators when such use was not required by the employer: On or about May 22, 2017, at the above addressed jobsite, the employer did not provide employees that voluntarily wear 3M 8110S N95 Filtering Facepiece Respirators with the information contained in Appendix D of 29 CFR 1910.134. |
|
Citation ID |
02002 |
Citaton Type |
Other |
Standard Cited |
19101200 E01 |
Issuance Date |
2017-08-15 |
Abatement Due Date |
2017-10-02 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.1200(e)(1): Employer had not developed or implemented a written hazard communication program included the requirements outlined in 29 CFR 1910.1200(e)(1)(i) and (e)(1)(ii): On or about May 22, 2017, at the above addressed jobsite, the employer did not develop and implement a written hazard communication program describing hazardous chemicals, such as but not limited to Portland cement (Titan America Portland cement), for employees performing plastering work. |
|
Citation ID |
02003 |
Citaton Type |
Other |
Standard Cited |
19260095 A |
Issuance Date |
2017-08-15 |
Abatement Due Date |
2017-09-11 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2018-01-12 |
Nr Instances |
1 |
Nr Exposed |
4 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.95(a): Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities, protective clothing, respiratory devices, and protective shields and barriers, was not provided, used, or maintained in a sanitary and reliable condition it was necessary by reason of hazards of processes or environment, chemical hazards, radiological hazards, or mechanical irritants encountered in a manner capable of causing injury or impairment in the function of any part of the body through absorption, inhalation, or physical contact: On or about May 22, 2017, at the above addressed jobsite, employees performing concrete plastering operations were not provided with gloves, exposing them to come in contact with Portland cement (Titan America Portland cement) which might cause skin irritation and dermatitis. |
|
|